Construction

New Event Center

 Artist's rendering of the new Event Center being constructed at The Oaks

Artist's rendering of the new Event Center being constructed at The Oaks

 

Construction Updates

 

June 29th, 2018 - We've received our first renderings of the new property! More pictures and construction updates will follow.


July 1st, 2018 - The foundation is in and we are on our way! 


July 31st, 2018 - Framing has begun! We are looking forward to the many beautiful events that will be happening in our new event center. Come out and enjoy a cocktail on the patio to check out the progress in-person.


August 2nd, 2018 - Check out the latest rendering of the new Event Center!


September 3rd, 2018 - Summer is winding down and construction is coming along nicely here at The Oaks Lakeside. The roofing system is being installed on our new Event Center and the contractors are busy getting the inside ready to go. Check out the pictures below and then come on out and have dinner on the patio - check out the progress for yourself!


October 1st, 2018 - The construction crews have hit their stride and we are on pace to hit our target of opening the Event Center in the Spring of 2019. Windows are in and a good part of the work has been completed. The exterior trades are hard at work trying to get wrapped up before winter comes!

November 1st, 2018 - Interior construction is on pace. Check out the pictures below!